PVE completes PM-1 Gas Plant Construction & Connections
Released
Released
Announcement PDF
Tuesday 16th May 2023
ABN 33 087 741 571
Po Valley Energy completes Podere Maiar gas plant construction; connects to Italian
gas grid
Highlights
•
Podere Maiar-1 (PM-1) gas plant development is complete and ready for commissioning
•
SNAM connections are complete, enabling delivery of PM-1 gas to the SNAM grid in Italy
•
Commercial arrangements complete, allowing PM-1 gas to be delivered under the gas
supply agreement (refer to ASX announcement 14/02/23)
•
With SNAM connection and transmission arrangements finalised, Po Valley Operations
(PVO) has initiated the process of recovering €757,000 performance bond funds (100%
basis - €476,910 net to PVO), previously deposited with SNAM
•
PM-1 gas plant construction and development achieved with only minor cost increases.
This result is particularly noteworthy given the current inflationary environment and
supply chain issues
•
First gas supply from PM-1 is contingent upon final operation and safety inspection. PVE
expects this prior to the end of the month
Po Valley Energy Limited (ASX: PVE) is pleased to announce the completion of its Podere Maiar
– 1 (PM-1) gas facility in the Selva Malvezzi production concession, located in the Po Valley
Region of Italy. The facility is now ready for commissioning and delivery of first gas, with
completion of these connections and commercial arrangements marking a significant milestone
for Po Valley Energy and its stakeholders.
Po Valley Chairman Kevin Bailey said: “Completion of the PM-1 gas plant development and
construction, along with the successful SNAM connections and commercial arrangements,
marks a significant achievement for PVE and its stakeholders. The PVE board visited the site in
late April and is impressed with the outstanding performance and dedication of the TESI and
PVO teams in a challenging supply environment.
“We extend our sincere congratulations to all those involved in its execution and appreciate the
cooperation and professionalism of SNAM throughout this process. PVE is well-funded to meet
all financial obligations and eagerly anticipates the commissioning and delivery of first gas to
the SNAM grid."
1
Figure 2 – Air & nitrogen tanks
Figure 1 – Dehydration columns
Figure 3 – Gas plant
The completion of SNAM connections and commercial arrangements paves the way for the
delivery of PM-1 gas to the SNAM grid in Italy. With these connections and arrangements in
place, PM-1 gas can now be delivered under PVO’s gas supply agreement, announced on
February 14th, 2023.
Additionally, the successful completion of the SNAM connection and transmission
arrangements has resulted in PVO initiating the process for the recovery of the performance
bond funds deposited with SNAM. The amount involved in this recovery process is €757,000
(100% basis), with €476,910 net to PVO.
Construction and grid connection has been largely completed on schedule and budget, with
only a 3% cost difference to budgeted expenditure. This amounts to ~€132,000 (100% basis),
€83,160 net to PVO. Given the global supply chain concerns the PVE board is delighted with this
outcome, as are the PVO joint venture partners.
Initial production of PM-1 gas is contingent on the signoff of the final operation and safety
inspection and final approval by Mase (Ministry of environment and energy security). PVE
expects that this will occur before the end of May 2023.
2
This announcement was approved for release by the Board of Directors of Po Valley Energy Limited
Enquiries to:
Mr Kevin Bailey AM
Po Valley Chairman
+61 417 556 458
Mr Aiden Bradley
Media & Investor Relations
+61 (0) 414 348 666
aiden@nwrcommunications.com.au
Registered Office
Rome Office
Suite 8, 7 The Esplanade
Mt Pleasant WA 6153
Australia
Via Isonzo 34,
Rome, 00198
Italy
TEL +61 (08) 9316 9100
FAX +61 (08) 9315 5475
TEL +39 06 4201 4968
FAX +39 06 4890 5824
Directors
Mr. Kevin Bailey AM, Chairman
Ms. Sara Edmonson, Non-executive Director
Mr. Joseph Constable, Non-executive Director
Ms. Katrina O’Leary, Non-executive Director