Po Valley Energy

Projects / Teodorico

Teodorico

100%
Owned by PVE
300,000
scm/day gas rate capacity
37 Bcf
Reserves (2P, attributable)
€67.2M
Capex, in total

Location

Sotto MarinaMar Adriatico
  • AR 94 PY Exploration Permit
  • d40 AC PY Production Concession
  • 12 nmi line
  • Hover a marker for details

Source: Po Valley Energy licence map. Recreated.

Proposed development concept

  1. Two wells

    With dual string completion

  2. Tripod well head

    Unmanned, minimal topside facilities, in 30m of water

  3. 12km tie-back

    To an existing offshore platform

  4. Naomi Pandora

    Owned and operated by Eni. Gas conditioning, processing and export

  5. Casalborsetti

    Gas terminal, via existing infrastructure

Proven by two discovery wells

Carola 1

62,000 scm/day

Recorded flow rate (1/4” choke)

Drilled to 2,620 m · 1986

Irma 1

131,000 scm/day

Recorded flow rate (5/16” choke)

Drilled to 2,572 m · 1988

Reserves & Resources*

Gas, Bcf
LicenceProjectReservesContingent ResourcesProspective Resources
1P2P3P1C2C3CLowBestHigh
AR94PYTeodorico**273748
Teodorico**7.410.614.0
PL3-C7.915.925.0
Podere Gallina (Net)***Selva2.68.418.8
Level A South0.71.12.3
Level B North2.25.611.2
Level B South0.62.25.9
East Selva18.321.925.6
Riccardina8.224.481.2
Fondo Perino6.49.212.9
Cadelbosco di SopraZini (Qu-B)1.12.74.6
Canolo (Qu-A)0.71.11.7
Canolo (Piliocene)0.43.610.5
Zini Qu-A0.61.42.4
Torre Del MoroTorre del Moro420.7502.0596.1

*Reserve and Resource estimated are as reported in CPR report dated 25 July 2022 (Refer ASX announcements 26 July 2022)

**The Reserves and Resources for Teodorico lie within the extended 12 mile development zone under the Pitesai, treatment of this is currently under discussion with the Ministry

***Net to the Company’s 63% economic interest in Podere Gallina

Read the full Teodorico description

The 100%-owned Teodorico (AR94PY) licence is located off the east coast of Italy, approximately 30km southeast of Venice and 40km northeast of Ravenna in the shallow waters of the Adriatic Sea.

This is a large field with a gas rate capacity of 300,000 scm/day. It received Environmental Approval in March 2021; however a Development Plan for Teodorico needs to be approved. Conceptually Teodorico could be developed with two wells with dual string completion. A proposed unmanned tripod well head with minimal topside facilities would be situated in 30m of water at the site. The platform conceptually would be tied back to and operated from an existing offshore platform 12km away at Naomi Pandora, which is owned and operated by Eni.

Teodorico gas conditioning, processing, and export onshore would happen from the Naomi Pandora platform. Gas would be piped to the Casalborsetti gas terminal using existing infrastructure. The Capex for this would be close to 67.2 million Euros in total, which would mean that the gas price would need to be above 10 Euro cents/scm to be economically viable. Currently, the gas price is multiple times this level. The Reserves (2P, attributable) are 37 Bcf, Resources (2C, attributable) 10.6 Bcf and Prospective (Best, attributable) are 15.9 Bcf[1].

Teodorico contains two gas discoveries drilled and tested by the former operator Eni. Carola 1: a discovery well drilled in 1986 to 2,620 m and recorded flow rates of 62,000 scm/day (1/4” choke), and Irma 1: a discovery well drilled in 1988 to 2,572 m and recorded flow rates of 131,000 scm/day (5/16” choke). At current prices, these flow rates would generate substantial revenues. The production forecasts would produce peak production per annum of 96.7 MMscm.

The Company is reviewing several options with Teodorico. It is a large asset that should be assessed as to the possibility of preparing it for the issue of a Production Concession and then exploring opportunities for Joint Venture or divestment. PVE will explore these avenues to determine the optimal outcomes for shareholders.

View the Development Ready Asset slide
Development Ready Asset