UPDATE ON SILLARO
Po Valley Energy Ltd (ASX: PVE) Italian based oil & gas exploration, development
and production company with interests in Northern Italy, wishes to update the
market on the workover on its Sillaro gas field.
Plans to perforate Level C1 in our Sillaro production field have been delayed due to
failures in the contractor’s perforation equipment.
Equipment was mobilised to Sillaro in the week ending 20 May and one perforation
was shot on a lower level of C1 however the perforation guns failed to fire on two
subsequent attempts. The contractor subsequently demobilised from site and is
expected to return in early June to complete the perforation of the target zone.