PVE - Recovers SNAM Performance Bond Funds Euro757k
Released
Released
Announcement PDF
Monday 29th May 2023
ABN 33 087 741 571
Po Valley Energy Successfully Recovers €757,000 Performance Bond Funds
Highlights
•
Po Valley Energy strengthens its cash position having successfully recovered €757,000
performance bond funds (100% basis - €476,910 net to PVO) previously deposited with
the Italian national Transmission System Operator SNAM
•
The return of the bond follows the completion of the SNAM pipeline tie in connection,
Gas Sales Agreement and transportation arrangements
•
First gas supply from Podere Maiar – 1 is contingent upon final Ministry approval after
final operation and safety inspection of the completed gas treatment plant
Po Valley Energy Limited (ASX: PVE) is pleased to announce that the process to recover the
performance bond funds deposited with SNAM has been finalised. The amount reimbursed
from SNAM is €757,000 (100% basis) with €476,910 net to PVO. This follows the completion of
the pipeline tie in connection to the newly built Podere Maiar – 1 (PM-1) gas treatment facility
in the Selva Malvezzi Production Concession, located in the Emilia Romagna region (Po River
Valley area in the north of Italy).
The return of the bond deposited with SNAM was conditional on completion of the SNAM grid
connection and the Gas Sales Agreement, announced on February 13th, 2023.
Initial production of PM-1 gas is contingent on Ministry final approval after the sign-off of the
final operation and safety inspection. The final inspection has been delayed due to severe
flooding throughout the Emilia Romagna region. Po Valley Energy has been informed that the
inspection will take place as soon as the Fire Department has attended to urgent priorities. The
gas treatment facility and preparatory activities for first gas have not been affected by the
flooding.
Po Valley Chairman Kevin Bailey said: “The return of the bond, in such a timely manner, is a
testament to the relationship the PVO team has built with SNAM throughout this process.
Additionally, it reflects that the facility is now ready for commissioning and delivery of first gas.
The delay of the final operation and safety inspection due to the flooding is entirely beyond the
control of our team. Currently the fire department are quite appropriately attending more
urgent matters in the Emilia Romagna region, however, we are assured that the inspections will
take place as soon as resources become available.”
This announcement was approved for release by the Board of Directors of Po Valley Energy Limited
1
Enquiries to:
Mr Kevin Bailey AM
Po Valley Chairman
+61 417 556 458
Mr Aiden Bradley
Media & Investor Relations
+61 (0) 414 348 666
aiden@nwrcommunications.com.au
Registered Office
Rome Office
Suite 8, 7 The Esplanade
Mt Pleasant WA 6153
Australia
Via Isonzo 34,
Rome, 00198
Italy
TEL +61 (08) 9316 9100
FAX +61 (08) 9315 5475
TEL +39 06 4201 4968
FAX +39 06 4890 5824
Directors
Mr. Kevin Bailey AM, Chairman
Ms. Sara Edmonson, Non-executive Director
Mr. Joseph Constable, Non-executive Director
Ms. Katrina O’Leary, Non-executive Director
2
Share your feedback
Discover